KA Donrath
Screw Pumps

Spaans Babcock received in 2012 the order from Stulz – Planaqua for the construction of a RAS pumping station with 3 Archimedean Screw Pumps and a Inlet Pumping Station with 3 Archimedean Screw Pumps as part of the the extension of the Sewage Treatment Works in Donrath Germany. All pumps were delivered with a steel trough.  The steel trough was backfilled with concrete by Spaans Babcock. After succsesfull performance trials the plant was handed over to the customer in October 2013.

Technical Data:

Data:
Installed Power [ Kw]:
Deisgn flow rate [m³ / s]:
2013
30
0,22
Angle [º]
Screw diameter [m]
35
1,1
Data:
Installed Power [ Kw]:
Deisgn flow rate [m³ / s]:
2013
37
0,38
Angle [º]
Screw diameter [m]
35
1,5

 

< Back to overview

Interested? Contact Us

Contact us